Riverfront Park Pavilion Work Has Begun

Work has begun on the Riverfront Park Pavilion.

A  seven-man crew from Schenkel Contracting, Fort Scott, began work on the Riverfront Pavilion Wednesday.

The pavilion will be 30 feet by 50 feet by 12 feet, Cory Schenkel said.

It is located near the parking area, at the entrance to the park.

The crew was putting up the building frame, with the roof slated for tomorrow, and the end wall following, he said.

The pavilion will have a concrete pad, lights, and some electrical outlets, and should be done in a few weeks, weather permitting, Schenkel said.

Schenkel will be completing the concrete work. Max Fanning, Fort Scott, is the contractor for the electrical work.

The pavilion, although it looks like it sits askew, runs north and south, Schenkel said.

 