FORT SCOTT — The playground at USD 234’s new preschool still has to be brought up to ADA rules, which call for paths at a 16-to-1 slope to each piece of equipment, construction manager Pat Wood told the board Nov. 9. Regrading the playground would mean taking out the equipment and the concrete around it.
Board members were told nothing in one contractor’s scope of work covered ADA or changing the grade. “You hire me to build your house, and the framing gets messed up, and I blame it on the printer,” one speaker said, comparing it to a builder blaming someone else.
One board member said the decision should not be made only to save money. “One thing that’s going to be important to me is that we just don’t make the decision in the short term to save money,” the board member said, asking whether looping paths around the equipment is what’s best for students and staff.
The playground is not part of the preschool’s bid documents, so it will not hold up construction, but a board member noted that a playground that doesn’t meet ADA rules could hold up the preschool’s opening. Either fix was estimated at four to six weeks. Wood hopes to put the preschool project out to bid this month, with bids due back before Thanksgiving and a July 1 completion date.
Read the district’s recap of the Nov. 9 meeting, or read the meeting transcript.