 A crack repair project on U.S. 69 in Fort Scott is underway this week. The 2.1-mile project area starts at 23rd Street and continues north to U.S. 54. Traffic is reduced to one lane at the work zone, according to a press release from KDOT.

“They are moving pretty fast on it,” said Priscilla Petersen,  public relations officer with the Kansas Dept. of Transportation in Southeast Kansas. “It is a crack repair with asphalt.”

“There are alternating lane closures for U.S. 69 traffic at the work zone. There should be no significant delays to traffic. The work should take one week, weather permitting,” she said.

 

Pavement Pro’s of McPherson is the contractor. The cost of construction is $81,593.

 

 