Following a fire at the Fort Scott Evergy Substation in August 2022 , Evergy is expanding its footprint.

Evergy is an electric utility company that serves eastern Kansas.

The company purchased property near Stanton Street and Old Fort Boulevard in March for the construction of a new substation, according to Kaley Bohlen, Evergy Communications Manager.

Evergy is currently located on Old Fort Blvd. on Skubitz Plaza and will expand their substation to the north and west of the current site.

Stanton Street is behind the current substation to the north and west.

Bohlen said Evergy doesn’t disclose real estate transactions, and are still reviewing options for access to National Avenue.

The existing Fort Scott Service Center utilized for personnel and offices will remain, according to Bohlen. Once the new Infantry Substation is built and operational, the existing Fort Scott Substation equipment and poles will be removed.

“The new Infantry Substation will be about 1.75 acres and will replace the former Fort Scott Substation that was damaged by fire last year,” she said. “The new substation will provide additional capacity to enhance electric reliability for the Fort Scott area, as well as strengthen the regional power grid. Automated switching capabilities and grid automation will help improve outage response times.”

“Construction has begun and is scheduled to be completed by the end of 2024,” she said. “Once the new substation is operational, we will decommission the current Fort Scott Substation and remove all structures and equipment that are no longer in use. The existing Fort Scott Service Center utilized for personnel and offices will remain. Once the new Infantry Substation is built and operational, the existing Fort Scott Substation equipment and poles will be removed.”

 