Resurfacing to begin on U.S. 69 in August

 

Timeline

Description automatically generated

Monday, Aug. 2, the Kansas Department of Transportation (KDOT) expects to begin a resurfacing project on U.S. 69 and U.S. 69B in Crawford County. Project activity includes a mill and overlay on U.S. 69 between U.S. 400 and K-47, excluding the section within the Pittsburg city limits. U.S. 69B is being resurfaced through the communities of Franklin and Arma.

Map

Description automatically generated

Work will start on U.S. 69B and then proceed south on U.S. 69 from the K-47 junction. Flaggers and a pilot car will direct one-lane traffic through the work zone; expect delays of 15 minutes or less.

Weather permitting, the project should be finished by early September.   KDOT awarded the construction contract of $2.3 million to Heckert Construction, Pittsburg. Persons with questions may contact KDOT Construction Engineer Kyler Farmer, (620) 308-7617, or Public Affairs Manager Priscilla Petersen, (620) 902-6433.

 

Leave a Reply

Your email address will not be published. Required fields are marked *