K-7 pavement repair project to start at Girard into Bourbon County

 

In early November, the Kansas Department of Transportation (KDOT) expects to begin a pavement repair project on a 500-foot section of K-7 at Girard. K-7 will be closed to traffic north of K-47. A state route detour will be signed on K-47, U.S. 69 and K-39 (see map).

 

Project activity includes repairs to the base drains and replacing the water lines and pavement. KDOT awarded the construction contract of $388,686 to Mission Construction, St. Paul. Weather permitting, the work should be completed by mid-December.

 

Persons with questions may contact KDOT Pittsburg Area Engineer Kyler Farmer at (620) 308-7617, or Public Affairs Manager Priscilla Petersen, (620) 902-6433. Check KDOT’s updated traveler information website, www.Kandrive.org, for more highway condition and construction details.

 