Progress On New Pool

Construction is proceeding rapidly on the new pool.  In three weeks the old structure has been removed and workers are currently digging out additional dirt for the new pool. As expected they have hit rock and are using a jack hammer on a backhoe to break it up.

Construction workers said that once they get everything dug out, they will lay in the drain line and then start pouring concrete. So far everything is on schedule. Weather is the biggest unknown and a large rain could significantly slow things down.

 